Broken Bars in Gantt Chart? Here is a simple trick to get rid of it.
Problem: While the remaining bar should be continuous from the actual bar, Often we see a gap between the data line and remaining bar. This can
be misunderstood easily and makes the schedule looks awful.

Solution: This is due to remaining work is scheduled
to next working day on your calendar. To avoid this, make sure you schedule the
data date with time to next working day.
In my example, My Current data date was 01 May 2011 00:00
Hrs. which is Sunday.
My current data date should be after the calendar holiday on
Monday 02 May 2011 08:00 Hrs
After rectification, the bars will look like this.
For more free scheduling tips and free videos please click
here https://www.xeduleacademy.com